Walnut Lane/Grant Avenue Roundabout Project Update
The Roundabout project is moving along as scheduled. The contractor, Vintage Paving, will be entering the phase of the project which will require the full closure of the intersection of Walnut Lane and Grant Avenue (SR 128), beginning Monday, November 13th . This road closure will be in effect Monday, 8am, through Friday at 3pm. The roadway will be opened during the weekends beginning at 3pm on Friday. The closure could be in effect for up to six weeks, depending on weather and other construction factors. A detour will be posted to direct traffic via East Baker Street around the work zone. Local traffic will be allowed access to Walnut Lane during these detour closures. Should you have any questions or concerns, please contact the individuals below:
Carol Scianna, Winters Environmental Services Manager (520) 794-6715 or carol.scianna@cityofwinter.org.
Project Resident Engineer, Michael Karoly, PE, (916) 960-6308 or mkaroly@willdan.com
We appreciate your patience and cooperation during construction.